DUSHANBE, Tajikistan, August 7. The Ministry of Energy and Water Resources of Tajikistan has announced a tender for the expansion of the Romit 110/20/10 kV substation.
The expansion will involve installing a new 110/35/10 kV power transformer with a capacity of 10 MVA, as well as a 110 kV outdoor switchgear and a 10 kV indoor switchgear. The contract is expected to be completed within six months.
This expansion is part of the "Electricity Network Construction Project in Romit – Phase II," which is funded by a grant from the Korea International Cooperation Agency (KOICA).
The tender, funded by KOICA grant funds, is open only to local companies.
Bids must be submitted to the address below by 3:00 PM (local time) on August 26, 2024.
Additional Information:
Address: 1st Floor, Room No. 9, Shotemur 27, Dushanbe, Tajikistan
Contact Person: Mr. Naim Rahimzoda
Phone: +992 372 35 97 78
Email: [email protected]