BAKU, Azerbaijan, November 8. Türkiye aims to reach a total installed capacity of 120 GW in solar and wind energy by 2035, but achieving this target will require significant investment in grid modernization, according to an analysis by UK-based energy think tank Ember, Trend reports.
The analysis highlights that unlicensed power plants - which make up 90% of Türkiye’s installed solar capacity and primarily serve self-consumption - have already strained the country’s electricity network. The transmission grid reached its capacity limits in September 2024, followed by the distribution network in July 2025.
To address these challenges, Türkiye’s Electricity Transmission Company (TEİAŞ) has outlined a 362 billion Turkish lira ($5.7 billion) plan for grid upgrades over its 2024-2028 Strategic Plan period. However, Ember notes that economic conditions have negatively affected contracts with contractors, leading to penalties and even exclusion from future tenders, which could slow progress.
The think tank also points out that Türkiye plans to spend $8.7 billion supporting domestic coal power plants through 2030 - 53% more than the entire five-year grid renewal budget. Ember suggests that redirecting resources from coal subsidies toward modernizing the transmission and distribution networks and constructing new substations would significantly accelerate progress toward the 2035 solar and wind targets.
According to Ember, prioritizing grid upgrades over fossil fuel support is essential if Türkiye is to meet its renewable energy ambitions and ensure a stable, sustainable electricity system for the future.