Astana, Kazakhstan, March 4
By Daniyar Mukhtarov - Trend:
The issues of the construction of a fourth oil refinery in Kazakhstan are still being studied, Chairman of Board of the Kazakh national oil and gas company KazMunaiGas, Sayat Mynbayev said at a briefing held in the Central Communications Service under the president of RK on March 4.
"The issue on the location and capacity of the fourth refinery is still being studied by specialists of the Oil Ministry and KazMunaiGas and I cannot give a definite answer," he said.
The board chairman of the national company recalled that currently three existing refineries in Kazakhstan which should be completed in 2016, are being upgraded resulting in gasoline demands for Euro-4 and Euro-5 standards being met until 2022.
"This is one side of my response to the question on the fourth refinery construction," Mynbayev said. "The planned capacity of the refinery should be at least five to six million tons per year. To construct a refinery with a capacity of less than that amount of oil makes no sense."
It is necessary to work out the issue of potential markets, for with the construction of the refinery the question of product export s will be raised, according to Mynbayev.
"Export to neighbouring Russia? Hardly. It has a surplus of production in its refineries. To China? Also hardly, as their refineries are competitive. To carry through the Caspian to the west is a complex logistic. There is Azerbaijan on the way with its refining facilities," he said.
The southerly direction can be considered as a potential market, but there is Russia and we will have to compete, according to the board chairman.
"Only after we study the situation will the question be raised on how much funding is required for this project and where to get it," Mynbayev said.
Translated by S.I.
Edited by S.M.