Azerbaijan, Baku / Trend corr. I.Khalilova / The Azerbaijani Ministry of Economic Development concluded a contract with the British company Curry & Brown to provide consultative services within the framework of the project to construct a hard waste plant, head of the Department on Investment Policy at the Ministry Askar Alakparov stated.
Under the contract the consultant is to develop, , a tender document to hire a contractor to construct within 16 weeks and manage the garbage processing plant. Tenders are expected to be announced in three weeks.
The Deputy Minister of Economic Development, Mikail Jabbarov, believes that the construction of the first incineration plant and the production of electric energy would be launched in the first quarter of 2008.
The document will be developed in three or four weeks and will be submitted to invite applicants to participate in the tender. They will be asked to submit their proposals within six weeks.
The Finnish Poyri company held a preliminary assessment of the proposals of the three companies for the Ministry of Economic Development, the Japanese EBARA, Austrian EVN and French CNIM.
The plant plans to construct a capacity of 500,000 tons which will include upgraded equipment and will meet international standards. Around 1mln ton of waste is annually collected in Baku and the surrounding areas. The project will be financed by the State budget.