BAKU, Azerbaijan, August 8. Construction of the runway and related infrastructure, considered the most important and technologically complex part of the project, as well as the installation of systems and equipment at Alat Airport, is almost 50 percent completed, the Alat Free Economic Zone said in response to Trend's inquiry.
This was reported by the Alat Free Economic Zone in response to Trend's inquiry.
Meanwhile, it was noted that the design of other airport infrastructure facilities and the preparation of the final version of the airport master plan have been successfully completed, and the construction of several related facilities has already begun:
"Thus, the construction of the fire and rescue station, which is of particular importance, is 45 percent complete and continues. The construction of a number of related facilities and the installation of the necessary systems and equipment are estimated to be 10-30 percent complete.
Moreover, it was noted that construction and installation work, ordering, manufacturing, and installation of the necessary equipment are being carried out in stages following the schedules drawn up:
All work is currently being carried out in full accordance with these schedules. Given the complexity of the project, the advanced technologies used, and the current capabilities of manufacturers, the full commissioning of Alat Airport is scheduled for early 2027.
What will this airport add to the country's transport infrastructure?
The information emphasizes that the new airport and the Cargo City international business logistics center, developed by the Silk Way group of companies in the Alat Free Economic Zone, are the main components of a multimodal center offering advanced transport and warehousing solutions:
"The Alat Logistics Center (ALC) will strengthen the supply chain by integrating air, rail, and ground transportation to ensure faster and more efficient cargo transportation. The Alat Free Economic Zone, by providing investors with more advantageous transport and logistics services, strengthens the conditions necessary for effective global trade. At the same time, the commissioning of the aforementioned airport and related logistics infrastructure will undoubtedly give impetus to the broader participation of our country as a whole and our transport sector in particular in the “Middle Corridor” project, which is a continuation of the Trans-Caspian International Transport Corridor connecting Asia and Europe, and will enhance its role, strategic importance, and significance.
“In addition, the contribution of the infrastructure solution being created to strengthening cooperation in the transport sector with the countries of Central Asia and increasing transport volumes will be very significant and will ensure its further dynamic development,” the information notes.
At the initial stage, it is planned to increase the airport's annual cargo turnover to 500,000 tons, and then to 1.5 million tons. Initially, its activities were focused on cargo transportation, but later it was decided to grant the airport international status. The airport will cover an area of 750 hectares.