Azerbaijan, Baku, Feb. 15 / Trend E.Ismayilov /
At present, daily production of oil from the Azeri-Chirag-Guneshli (ACG) field in the Azerbaijani sector of the Caspian Sea hit about 850,000 barrels per day, BP said today
PSA on ACG was signed in September 1994. The duration of the agreement is 30 years. Production from Chirag field begun in 1997, the Central Azeri - early 2005, Western Azeri - early 2006, East Azeri - late 2006. The oil production on deep-water Guneshli is expected to start in mid 2010.
Shareholders of the Azeri-Chirag-Guneshli development project are: BP (operator - 34.1%), Chevron (10.2%), SOCAR (10%), INPEX (10%), Statoil (8.6%), ExxonMobil (8%), TPAO (6.8%), Devon (5.6%), ITOCHU (3.9%), Hess (2.7%).
In 2009, SOCAR exported about 2.8 million tons via the Baku-Supsa compared to 407,100 tons in 2008.In 2007, the company did not transported oil in this direction because of repairs on the pipeline since November 2006. Supply via the pipeline started in mid-2008, but because of the Georgian-South Ossetian conflict, this process was suspended. Transportation via the pipeline was restored in early November 2008.
Construction of the pipeline began in April 2003 and was commissioned in 2006. Total construction expenses for oil pipeline hit $2.977 billion
The total length of BТС is 1.768 kilometers including the 443 kilometer section running via Azerbaijan, the 249 kilometer section via Georgia and the 1.076 kilometer via Turkey.
The shareholders of BTC are BP (30.1%), AzBTC (25%), Chevron (8.90%), Statoil (8.71%), TRAO (6.53%), ENI (5%), Total (5%), Itochu (3.40%), Inpex (2.50%), ConocoPhilips (2.50%) and Hess (2.36%)