Baku, Azerbaijan, Nov. 25
By Fatih Karimov - Trend:
The first unit at the gas sweetening refinery at Iran's South Pars gas field's phases 15 and 16 started production yesterday, the Mehr News Agency reported on November 25.
Development operations of the two phases began over six years ago. Due to a likely gas shortage during winter, the refinery has started production using input gas from phases 6-8 of the South Pars field.
The refinery is projected to produce 10-12 million cubic meters of gas to the national gas network per day in order to help secure a sustainable supply of gas during the winter.
Development of the two phases has progressed by 95 per cent. The two phases are projected to produce 50 million cubic meters of gas, 80,000 barrels of condensates and 400 tons of sulphur per day as well as one million tons of liquefied gas per year.
In August, ISNA quoted Iranian Oil Minister Bijan Namdar Zanganeh as saying that phases 15 and 16 of the South Pars gas field may come on stream in the second half of the next Iranian calendar year which starts on March 21, 2014.
Zanganeh said the Oil Ministry has a special focus on completing and inaugurating South Pars' gas field phases 12, 15, 16, 17 and 18.
South Pars is a joint gas field owned by Iran and Qatar. The field on the Iranian side holds 14 trillion cubic meters of gas and has been divided into 29 phases where phases 1 to 8 have been completely developed, Phases 9 and 10 has been operated, but not to full capacity and phases 11 to 29 are under construction.
During the past three years from the inauguration of Phases 9 and 10, these have not been developed completely and their output in total is 42mcm/d, instead of the anticipated 50mcm/d.
The development process of phases 27 and 28 have not been started, while based on an official announcement from the Pars Oil and Gas Company in April, some of the South Pars phases have been partially completed. These are phase 13 by 61 per cent, 14 by 47 per cent, 19 by 61 per cent, phases 20-21 by 46 per cent and phases 22-24 by 60 per cent.
So far, $46 billion has been invested in phases 11-24 of the gas field, but no single phase has come on stream yet. This is while the total investment in phases 11 to 24 of South Pars had been estimated to be less than $40 billion.