Azerbaijan, Baku, Feb. 27 / Trend A.Akhundov /
The World Bank (WB) defines purposes and scope of work under agriculture development and lending program phase III in Azerbaijan, the WB Baku Office told Trend on Monday.
"Due to the fact that the scope of the project is unknown, volume and timing of funding have not yet been clarified. This will be determined at the last phase of the project. We are now at the stage of defining the objectives and activities," the bank said.
According to preliminary data, the WB plans to allocate to Azerbaijan on the implementation of the Phase III about $35-40 million.
The funding was specified during the visit of the World Bank mission led by the manager of agricultural projects Dina Umali-Daninger to Baku in late January.
"On the basis of discussions, according to the regulations, further discussions are expected. Upon completion of the drafting process it will be possible to begin formal negotiations. While the project is not ready, so it's not known when it will be submitted for approval of the Bank's Board of Directors," the WB said.
The loan will be granted from the funds of the International Bank for Reconstruction and Development (IBRD is part of the World Bank). Its terms will be specified during the negotiations. Until now, the agricultural projects in Azerbaijan were financed on concessional terms, through the International Development Association (IDA). At present, Azerbaijan has no access to its funds.
The project is expected to be approved in 2012.
The development of the concept was launched within the second phase of the adapted program. Its implementation will be completed in February 2012.
Implementation of this project contributes to increasing farmers' revenues and productivity of agricultural enterprises. The implementation of the second project started in 2007, it is designed for 4 years.
The total cost of the project is $59.5 million, $29.2 million of which is the WB's loan. International Development Association (IDA) allocated $20.5 million. Some $8 million are allocated at the expense of IDA toughened terms.
The government allocated $12.6 million, Japan PHRD technical assistance grants program - $1.61 million, turnover means - $9.56 million, funds of financial mediators - $4.7 million.
As of September 2011, the amount of funds provided by the World Bank, resulting from differences in exchange rates, increased from $29.2 million to $32.1 million of which $31 million was spent. The balance is $1.1 million.
Under the implementation of the second phase of adapted program of agriculture development and lending, 46,000 small loans worth 62 million manat were allocated. This led to increase in investment volume in rural areas. Medium size enterprises in the agricultural business were allocated 110 investment loans worth $17 million. Also 74 grants were allocated to introduce and transfer advanced technologies under the second phase.
The project consists of two components. The cost of the first component hits $42 million. It is designed to support agricultural business services. It is planned to strengthen the financial services in the regions, in particular the activity of credit unions that were created within the first phase of the program. The potential of local banks is planned to be strengthened.