BISHKEK, Kyrgyzstan, February 18. The second hydro unit at Uch-Kurgan Hydroelectric Power Plant (HPP) in Kyrgyzstan will be handed over for reconstruction, starting from March 1, 2025, Trend reports.
According to the Ministry of Energy, the project will be carried out by China National Electric Engineering Company. After the reconstruction, the capacity of this hydro unit will increase by 9 MW.
The Uch-Kurgan HPP has four hydro units, each with a capacity of 45 MW. In 2024, the fourth hydro unit underwent reconstruction, resulting in an increase of 16 MW in its capacity. Currently, the total capacity of the HPP stands at 189 MW. The existing hydro units have not been renovated since the plant's construction in 1962.
With the reconstruction of the hydro unit underway, the overall capacity of the Uch-Kurgan HPP will be temporarily reduced by 45 MW. The reconstruction is expected to be completed by December 2025.
The Ministry of Energy reported that in order to ensure the successful passage of the autumn-winter period and the uninterrupted supply of electricity to the population, it has already held preliminary negotiations with neighboring countries regarding electricity imports as an alternative solution. The Ministry is urging the public to use electricity sparingly, given that the mentioned hydro units have been taken offline for reconstruction.