BAKU, Azerbaijan, August 6. AzerEnergy OJSC has issued a tender for the preliminary design, tender documentation, technical specifications for identifying optimal locations, detailed design, and construction of a 250 MW battery energy storage system (BESS) in the Azerbaijan power grid.
The participation fee is 350 manat ($206).
Tender submissions are due by 10:00 a.m. (GMT +4) on August 30, 2024.
The tender packages will be opened on August 30, 2024, at 10:00.
Additional Information:
Phone: (+99412) 490-09-27; 598-26-96
Contact: Hemid Isazade (hemid. [email protected])
Address: 10 Academician A. Alizade street, Baku