BAKU, Azerbaijan, Sept.6
By Leman Zeynalova – Trend:
Azerbaijani gas was for the first time delivered to Europe with the launch of the Southern Gas Corridor (SGC) in December 2020, thereby making a significant contribution to the continent’s energy security. Italy, which is so far supposed to be the largest importer of Azerbaijani gas via this corridor, also managed to export some of these volumes. The European leg of the Southern Gas Corridor, i.e. the Trans Adriatic Pipeline (TAP) is said to speed up transition to cleaner energy, reduce natural gas prices in the European market and increase overall competitiveness.
With initial capacity of 10 billion cubic meters per year, TAP is projected to supply 8 billion cubic meters of gas to Italy and 1 billion cubic meters of gas to Greece and Bulgaria each. The pipeline is estimated to have delivered over 3 billion cubic meters of gas so far. The International Energy Agency (IEA) expects that TAP will reach 10 billion cubic meters of capacity per year in the next two years.
There are a number of projects envisaging connection to the Trans Adriatic Pipeline, with the Interconnector Greece-Bulgaria (IGB) being much closer to commissioning.
The IGB project enables the transmission of gas and supplies from new sources, making it key to Bulgaria's energy security and part of the national plan for diversification of gas sources. The capacity of the project is 3 billion cubic meters with the option to reach 5 billion cubic meters. Half of the capacity of the interconnector is already reserved, as four of the shippers are completely new to the Bulgarian market. A contract has been signed for the supply of 1 billion cubic meters from Shah Deniz 2 based on a long-term contract with Bulgargaz.
The conclusion of the contract for construction of the interconnector dates back from the end of 2019, as one of the main commitments of the project company in structuring IGB is the obligation to control costs within the approved budget, which will ensure competitive transmission for customers. The delay in construction activities and the approved update of the construction schedule for the end of 2021 are due to objective reasons related to the global coronavirus pandemic and do not lead to direct losses. The established alternative route through the Greek system and Siderokastro provides a temporary solution for servicing the contract with Azerbaijan until IGB is put into commercial operation.
Due to the ongoing construction of the Interconnector, the delivery point Komotini was not put into commercial operation as of the commencement date for supplies under the Agreement – 31.12.2020., and is expected to enter commercial operation in the middle of 2022. This required the execution of negotiations with the Azerbaijani supplier, which resulted in achieving an agreement for a temporary use of another delivery point on the territory of Greece and transportation of natural gas to Bulgaria through an alternative route for the period from 31.12.2020 to 30.09.2021.
Construction activities continue with a steady pace – over 165 km are welded, 110 km are lowered, trenching and backfilling are ongoing according to schedule. After the successful HDD crossing under the Maritsa river, field teams have initiated preparation for the process under Studen Kladenets Dam. The EPC contractor indicates that the completion of the linear infrastructure will be within the agreed deadline as per the signed contract.
Ionian Adriatic Pipeline (IAP)
Ionian Adriatic Pipeline can be connected to the Trans Adriatic Pipeline (TAP) to transport gas to many countries in South-East Europe. The pipeline with total length of 516 kilometers will stretch from Albania through Montenegro, and Bosnia and Herzegovina, to split in Croatia. The capacity of the pipeline will amount to five billion cubic meters of gas per year.
The European Commission says that Ionian Adriatic Pipeline is set to be commissioned in 2025. The operative promoter of the project in Croatia is Plinacro, which has prepared complete documentation for the establishment of the IAP-project company and its headquarters in Dugopolje, Croatia. Given the situation with the COVID-19 pandemic, these activities have slowed down. However, Plinacro applied the project for the 5th PCI list to be adopted by the end of 2021. Also, the project is highlighted in the EU enlargement documents and is particularly important because of the gasification of Montenegro and the opening of a new supply route for Bosnia and Herzegovina.
BRUA (Bulgaria - Romania - Hungary – Austria)
BRUA gas pipeline, together with the Interconnector between Romania and Bulgaria, is an important link between the Southern Gas Corridor and Central Europe and the Balkans. The first stage of development of the BRUA gas pipeline was completed in November 2020, according to the implementation schedule, without any delays. The pipeline will ensure an adequate degree of interconnection with neighbouring countries and will create a new natural gas transmission route at regional level, from various sources of supply including the Caspian Sea area. Earlier, Romania’s Minister of Energy Virgil Daniel Popescu said Romania hopes to resume the bilateral talks with the Azerbaijani authorities to reach their agreement on the conclusion of a Memorandum of Understanding to analyze the opportunities for using the transport infrastructure offered by the RO-BG Interconnector and the BRUA gas pipeline in the future stages of the Southern Gas Corridor given the positive trade impact for the two sides and the importance of strengthening regional energy security.
Serbia-Bulgaria gas interconnector Nis-Dimitrovgrad
Serbia seeks to diversify its sources of gas supply, and is interested in the possibility of supplying natural gas from Azerbaijan. This year, Serbia will start the construction of the Serbia-Bulgaria gas interconnection, which should become operational in 2023. With this interconnection, Serbia will be able to connect with other potential suppliers, including gas pipelines on the Southern Gas Corridor – TANAP and TAP.
The Project consists of the construction of a 109 km-long underground gas transmission pipeline with the associated infrastructure above ground. It has been signed in May 2021 in Serbia, combined with European Union’s IPA fund for Serbia amounting to €49.6 million.
The European Investment Bank (EIB) has provided a long maturity for the loan to finance the Serbian section of the Niš-Dimitrovgrad gas pipeline (Serbia-Bulgaria interconnector).
North Macedonia-Greece interconnector
The pipeline links the Nea Mesimvria valve station of the Greek gas transmission system in the northern port city of Thessaloniki with Gevgelija located directly on the Greek-North Macedonia border. This Project at the last Ministerial Meeting of the Energy Community was selected as a Project of Common Interest for 2020. It aims at gas connection of the country with Greece and the Southern Gas Corridor in order to supply the country with natural gas from diversified sources of supply and, inter alia, from the gas fields in Azerbaijan.
---
Follow the author on Twitter: @Lyaman_Zeyn