BAKU, Azerbaijan, October 14. The Trans Adriatic Pipeline (TAP) AG consortium has released detailed information on firm capacity allocations for its interconnections, Trend reports.
On October 14, the allocated capacity at the Kipoi interconnection reached 388,941,292 kilowatt-hours (kWh). The consortium has also published tables outlining capacity allocations from October 14 to October 20, providing a comprehensive breakdown of forward capacity commitments.
These allocations highlight TAP’s commitment to transparency and its role in ensuring a stable and reliable energy supply across Europe.
Capacities for Kipoi:
|
Date |
Reserved forward firm capacity (kWh) |
|
October 14 |
388,941,292 |
|
October 15 |
341,019,866 |
|
October 16 |
341,019,866 |
|
October 17 |
341,019,866 |
|
October 18 |
341,019,866 |
|
October 19 |
341,019,866 |
|
October 20 |
341,019,866 |
Capacities for Komotini:
|
Date |
Reserved forward firm capacity (kWh) |
|
October 14 |
28,674,418 |
|
October 15 |
28,674,418 |
|
October 16 |
28,674,418 |
|
October 17 |
28,674,418 |
|
October 18 |
28,674,418 |
|
October 19 |
28,674,418 |
|
October 20 |
28,674,418 |
Capacities for Nea Mesimvria:
|
Date |
Reserved forward firm capacity (kWh) |
|
October 14 |
43,346,301 |
|
October 15 |
43,346,301 |
|
October 16 |
43,346,301 |
|
October 17 |
43,346,301 |
|
October 18 |
43,346,301 |
|
October 19 |
43,346,301 |
|
October 20 |
43,346,301 |
Capacities for Malendugno:
|
Date |
Reserved forward firm capacity (kWh) |
|
October 14 |
329,999,997 |
|
October 15 |
271,999,147 |
|
October 16 |
271,999,147 |
|
October 17 |
271,999,147 |
|
October 18 |
271,999,147 |
|
October 19 |
271,999,147 |
|
October 20 |
271,999,147 |
The Trans Adriatic Pipeline (TAP) transports natural gas from Azerbaijan's vast Shah Deniz field in the Caspian Sea directly to Europe. Stretching 878 km, TAP connects to the Trans Anatolian Pipeline (TANAP) at the Turkish-Greek border in Kipoi, traverses Greece and Albania, crosses the Adriatic Sea, and makes landfall in southern Italy.
TAP is essential for securing Southeastern Europe’s energy supply by connecting with both current and future interconnectors. A key link is the Interconnector Greece-Bulgaria (IGB), which began commercial operations in October 2022, delivering Caspian gas to Bulgaria and enhancing regional energy security. TAP’s connections through Greece and Albania, along with its Italian entry point, open up extensive possibilities for expanding the flow of Azerbaijani gas into larger European markets.
Follow the author on X: @Lyaman_Zeyn