BAKU, Azerbaijan, February 12. Shah Deniz 2 project is currently progressing with the East North well completion operations, Trend reports via bp.
In 2023, the Shah Deniz 2 project progressed towards the production start-up from the East North flank in early 2024.
“The project successfully completed the East North flank loop commissioning and system handover activities and is currently progressing with the East North (EN03) well completion operations, subsea execution and commissioning scopes,” said the company.
In the fourth quarter of 2023, the project also started up two new wells on the West South flank.
Shah Deniz participating interests are: bp (operator – 29.99%), SGC (21.02%), LUKOIL (19.99%), TPAO (19.00%) and NICO (10.00%).